Major stormwater project completed

On books for years, designed to alleviate flooding issues around Watson’s Golf Drive

By Mallory Panuska
Times West Virginian

FAIRMONT After years of aspiring and planning and about four months of construction, the first major project funded by the city’s stormwater utility officially wrapped up last week.

The project replaced and upgraded stormwater pipes in the Watson area and has been on the books for years, city officials said.

Mike DeMary, the city’s stormwater program coordinator, said about six homes on and around Golf Drive were experiencing significant flooding issues in their garages and basements for years and this project, which began in May, addressed those issues.

“We feel it was a good project. It will do what it was designed to do, keep water from entering people’s houses and basements and directing it toward the stream,” DeMary said. “There are probably half a dozen homes in that area that would get water in their basements and garages during heavy rain events.”

City utilities manager Dave Sago said that since the legwork of the project has been finished, there have not been any complaints of flooding from the residents in the area, even after several heavy rainstorms during the summer.

“Even with some of hard rains we’ve had it looks like it’s carrying water away like it’s supposed to,” Sago said. “We hope it’s going to accomplish what we set out for it to do.”

The majority of the project was completed by Cook Brothers Building Company. And last week, the project was finalized by C.W. Stickley with a paving job on Golf Drive.

“The final piece of the puzzle is getting the pavement down to divert water into the road crossings,” Sago explained.

In total, DeMary said the project cost more than $400,000, which up until several years ago would have been beyond the city’s budget. But in 2005, the city started charging a monthly surcharge on the utility bills of customers living within the city’s watershed area to pay for necessary upgrade projects.

The money derived from this fund paid for the project in full, and without that money, officials said this project and other projects slated for the future, would not have been possible.

Last month, the sanitary sewer board received a list of possible projects to be completed after Golf Drive, but DeMary said the board has not yet chosen which one to tackle first.

Currently, DeMary said the stormwater utility is working on routine maintenance and some smaller in-house jobs as officials consider the next project.

Included on the list are projects on Stony Road, Mary Lou Retton Drive at Gilbob Street, Lower Hillcrest Drive at Route 250, Ridgeley Avenue, and Dixie Avenue from Mound to The Drive.

E-mail Mallory Panuska at mpanuska@timeswv.com.

print this story  

Photos


Workers from C.W. Stickley paved Golf Drive last week as the final step in a more than $400,000 stormwater project in the works in the Watson area over the past four months. This was the first major project completed with money from the city’s stormwater utility, and should stop flooding in the garages and basements of residents in the area. PHOTO BY DANNY SNYDER/Times West Virginian (Click for larger image)



autoconx
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Premium Jobs

Early Learning Center Supervisor
Early Learning Center Supervisor - Supervisor needed to direct all activities and operations, including regulatory, budg...>MORE

HOSPICE AIDE - FT
Tender Loving Care

Recruiting now for the
following position in our
ANMOORE hospice agency:
...>MORE

MEn & Women
SPORTS MINDED
SALES
MEN & WOMEN
 
Rapidly growing company, representing a national sales organizatio
...>MORE

Physical Therapy Assistant
Physical Therapy Assistant - Mountain State Physical Therapy is now accepting applications for a Full Time Licensed PTA ...>MORE

Customer Service Professionals
Customer Service Professionals
Receive in-bound
calls only!

Nothing is sweeter than a great career,
...>MORE

Sales Professional.
Jack’s Furniture Center seeks full-time
Sales Professional for showroom sales.
Excellent commission plan plus
...>MORE

Administrative Secretary
Pierpont Community and Technical College is seeking to fill the full time position of Administrative Secretary.  Please ...>MORE

Tow Truck Driver
Tow truck dri vers needed Full Time. Apply at Marks Sunoco & Towing, 2395 WhiteHall Blvd.
WhiteHall WV 366-5765
...>MORE

adjunct positions
Fairmont State
University invites applications for adjunct positions for the January, 2010 semester.  Areas of ...>MORE

Drivers
Driver Wanted

AIRGAS MID AMERICA,
a leading distributor of
industrial, medical, &
specialty ga
...>MORE

See all ads


 

Community Newspaper Holdings, Inc.CNHI Classified Advertising NetworkCNHI News Service
Associated Press content © 2009. All rights reserved. AP content may not be published, broadcast, rewritten or redistributed.
Our site is powered by Zope and our Internet Yellow Pages site is powered by PremierGuide.
Some parts of our site may require you to download the Flash Player Plugin.
View our Privacy Policy
Advertiser index